Saturday, November 26, 2005

Stucco

Finishing around 2nd floor window
A spell of fine, fair weather means that we can get the stucco finishing work done around the windows & doors in the exterior dormer spaces. I believe this is the last step before painting the exterior. We'll keep our fingers crossed for clear weather!

Thursday, November 17, 2005

Hiatus

Work is at a total standstill on the dome, because....

...it's hunting season! D'oh! I should have anticipated that we wouldn't see anyone this week. Next week should mark a return to actual activity.

Tuesday, November 08, 2005

Attic & Front Door

Steve & the guys framing the open area in front of the bathroom ceiling
Clearly we have hit one of those lulls common in building, when nothing much seems to be happening because everything that actually is happening seems too trivial to photograph. There's still a bunch of little things that have to be done before drywall, but the main thing going in right now is the second-floor ceiling. We'll have some storage space up in the attic, but it will be only partly useable because the dome curve is flattening out pretty sharply by the time you get that high up. Still, a good spot to stash those boxes of seasonal decorations & the like.

Mr. Cheerful welcomes you all to the DomeThe other big development: We have a front door! It is an unfinished wood double door, actually; it will be finished with a medium-oak stain, making it darker than it looks here. I have no idea why Mike looks so grumpy in the picture. Perhaps he is contemplating all the painting/staining/finishing work looming in the near future.